  • Pregunta: Problem Duration (Months) Costs (sooo's) Penalty per month Normal crashed Activity Predecessor Normal Minimum < A 4 3 2,000 3,000 B 6 4 3,000 5,000 с 8 7 1,000 2,000 D 5 4 4,000 6,000 E 6 4 2,000 3,000 F CD 4 3 2.500 5.000 G FE 4 2 3,000 4,000 H 5 4 5,000 10,000 1 7 4,000 6,000 4 3 3,000 A construction project consists of a series of 10 activities that must


    student submitted image, transcription available below
    student submitted image, transcription available below
    student submitted image, transcription available below
    student submitted image, transcription available below
    student submitted image, transcription available below
    student submitted image, transcription available below
    student submitted image, transcription available below
    student submitted image, transcription available below
    student submitted image, transcription available below
    student submitted image, transcription available below
    Muestra el texto de la transcripción de la imagen
  • Chegg Logo
    Esta es la mejor manera de resolver el problema.
    Solución
    100(1 calificación)

    Answer= The critical path is=B-D-E-G-I-J Reaon- The network diagram is as below- Different paths and their durations= Critical path= path with maximum duration= B-D-E-G-I-J   Answer=

    Mira la respuesta completa
    answer image blur
Texto de la transcripción de la imagen:
Problem Duration (Months) Costs (sooo's) Penalty per month Normal crashed Activity Predecessor Normal Minimum < A 4 3 2,000 3,000 B 6 4 3,000 5,000 с 8 7 1,000 2,000 D 5 4 4,000 6,000 E 6 4 2,000 3,000 F CD 4 3 2.500 5.000 G FE 4 2 3,000 4,000 H 5 4 5,000 10,000 1 7 4,000 6,000 4 3 3,000 A construction project consists of a series of 10 activities that must be performed before the project can begin operation . WAN HI 2,000 A construction project consists of a series of 10 activities that must be performed before the project can begin operation Un proyecto de construcción cosiste de una serie de 10 actividades que tienen que ser realizadas antes de que el proyecto pueda comenzar la operación Construct an activity precedence diagram and answer the following questions, Construye un diagrama de precedencia de actividad y contesta las siguientes preguntas What is the critical path of the project? Indique cual es la ruta crítica del proyecto. O a B-D-E-G-1-) O b. B-D-F-G-1-) OCA-C-F-G-I- Od B-D-E-G-H-) How much can activity C be delayed before the project is delayed? Indique cuanto puede atrasarse la actividad C antes de que el proyecto se retrase. O a. 1 month b. 4 months O c 7 months d 2 months Which activities are not in the critical path? Indique que actividades no están en el paso crítico. O a.B, F, G, H Ob A, B, C, F OCB, C, F, H Od A, C, F, H What is the cost of cutting activity D one month? Indique cual es el costo de cortar la actividad D por un mes. O a $ 500 Ob $1,000 Oc$ 2,000 Od $ 5,000 In terms of marginal cost analysis, which activities should be considered for reduction first? En términos de análisis de costo marginal, indique cuales actividades deben ser consideradas para reducirlas primero. O a Activities Hand O b. Activities C and E O c. Activities G and H O d. Activities E and What of the following is a requirement to select the activity that would be cut? Indique que de lo siguiente es un requerimiento para seleccionar la actividad que sería cortada. O a. The activity must have a high duration time. La actividad debe de tener un tiempo de duración largo. Ob Cutting the activity should not change the project duration Cortar la actividad de modo que no corte la duración del proyecto, O c The activity must have a low duration time. La actividad debe de tener un tiempo de duración corto. Od. The activity must reside in the critical path. La actividad debe de estar contenida dentro de la ruta crítica. If we cut activity E by one month, what is the overall result? Indique cual seria el resultado de cortar la actividad E por un mes. O a. The project duration is cut by two months. La duración del proyecto se acorta por dos meses. Ob A parallel critical path is established with activity F. Una ruta critica paralela se establece con la actividad F. OC. A parallel critical path is established with activity H. Una ruta crítica paralela se establece con respecto a la actividad H. Od Answers a. and b. Las contestaciones a yb. What activities must be cut and by how much to attain a 3 month project reduction from the original problem? Indique cuantas actividades deben de ser cortadas y por cuanto para lograr una reducción de 3 meses a partir del problema original. O a Cut activity E by 1 month and activity by two months. Corta la actividad E por un mes y la actividad por dos meses. Ob. Cut activity E by 3 months. Corta la actividad E por 3 meses. Oc Cut activity E by 2 months and activity G by one month. Corta la actividad E por dos meses y la actividad G por un mes. Od. Cut activity E by 1 month, activity by one month and activity G by one month. Corta la actividad E por un mes, la actividad ) por un mes y la actividad G por un mes,