  • Pregunta: \table[[Activity,Time (weeks),\table[[Immediate],[Predecessor(s)]],Activity,Time (weeks),\table[[Immediate],[Predecessor(s)]]],[a,m,b,a,m,b

    \table[[Activity,Time (weeks),\table[[Immediate],[Predecessor(s)]],Activity,Time (weeks),\table[[Immediate],[Predecessor(s)]]],[a,m,b,a,m,b
    student submitted image, transcription available
  • Chegg Logo
    Hay 3 pasos para resolver este problema.
    Solución
    Paso 1

    solution:

    Given activities and their time estimates:



    a

    m

    b

    Activity

    immediate predecessors

    Time (weeks)

    A


    9

    10

    11

    B


    4

    10

    16

    C

    A

    9

    10

    11

    D

    B

    5

    8

    11

    Calculate the expected time (μ) and the variance (σ2)