  • Pregunta: \table[[Activity,Time (weeks),\table[[Immediate],[Predecessor(s)]],Activity,Time (weeks),\table[[Immediate],[Predecessor(s)]]],[a,m,b,a,m,b

    \table[[Activity,Time (weeks),\table[[Immediate],[Predecessor(s)]],Activity,Time (weeks),\table[[Immediate],[Predecessor(s)]]],[a,m,b,a,m,b
    student submitted image, transcription available
  • Chegg Logo
    Hay 3 pasos para resolver este problema.
    Solución
    Paso 1

    Let's start solving the question with an explanation:

    Activity

    Expected Time

    Variance

    A

    9.83

    1.69

    B

    10.17

    0.69

    C

    4.69

    1.38

    D


    8.67

    17.78

    b

    6.95

    6.47


    Explanation:

    The expected completion time of the critical pa...