  • Pregunta: Build the network of nodes for the project. What is the minimum cost to accelerate in 4 days the following project managed by Juan Mercado at NY State University? (You must do the network of nodes to determine the critical path)

    Build the network of nodes for the project. What is the minimum cost to accelerate in 4 days the following project managed by Juan Mercado at NY State University? (You must do the network of nodes to determine the critical path)
    student submitted image, transcription available below
    Muestra el texto de la transcripción de la imagen
  • Chegg Logo
    Esta es la mejor manera de resolver el problema.
    Solución
    100(2 calificaciones)
    Te mostramos cómo abordar esta pregunta.

    To get started, construct the project network diagram using the given activities and their respective precedences.

    Project Network Diagram: Path AD = 11 days Path CE = 12 days   Critical path = CE Project Duration = Duration of Critical path = 12 days Desired Duration = 12 - 4 = 8 days

    Mira la respuesta completa
    answer image blur
Texto de la transcripción de la imagen:
Construya la red de nodos para el proyecto Cuál es el costo minimo de acelerar en 4 dias el siguiente proyecto que administra Juan Mercado on NY State University? (Debe hacer la red de nodos para determinar la ruta critica) (Seleccione la alternativa correcta y suba en la plataforma por Mensajeria el proceso completo) Actividad Tiempo normal (días) Tiempo de aceleración (días) Costo Normal Costo de Aceleración Precedentes inmediatos 6 15 $900 $1,000 B 8 6 < OO с 4 3 $300 $500 5900 $1,000 $400 $600 $1,200 $1,600 D 5 3 A E 8 5 C @ 100 200 400 O 750 0 1100